Improvements to Thamarasserry Varattiakkal road in Kozhikode District - Balance work

Spent on this package so far

₹10.09 crore

₹10,08,74,371

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Works (1)

Thamarassery Varattiakkal Road

Completed
100%Physical progress
95.7%Financial progress
Scheduled start10-03-2023
Scheduled completion28-09-2024
Implementing agency (SPV)
KRFB
Contract amount
₹11,00,97,608₹11.01 crore
Amount paid
₹10,53,37,854₹10.53 crore
Paid to contractor
₹9,95,56,969₹9.96 crore
Administrative sanction (AS)
₹25,00,00,000₹25 crore
Financial sanction (FS)
₹40,57,31,197₹40.57 crore
Technical sanction (TS)
₹11,00,97,608₹11.01 crore
Tender amount
₹10,11,41,296₹10.11 crore
Current progress
DBM completed upto 14.671km in the first stretch .drainage completed.BC to be done. In the second stretch DBM completed (Varattiakkal to CWRDM). BC to be done. Work terminated on 08.04.2022 with risk and cost of contractor.Balance work tendered on 17/6

Money trail

Estimated amount
₹40,57,31,197Estimate of sub-project PWD004-18, shared by 2 contract packages
Expenditure reported · this package
₹10,08,74,371
Expenditure reported · all 2 packages
₹30,37,25,52774.9% of the estimated amount

Details

Project code
PWD004-18-03
Department
Public Works
Constituency
KunnamangalamMLA: Shri P. T. A. Rahim
Constituency
Koduvally

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Improvements to Thamarasserry Varattiakkal road in Kozhikode District”. The figures below are for that whole project, not this package alone.

Approved
₹40,57,31,197₹40.57 crore
Paid so far
₹32,87,64,54981% of the amount approved

Source: KIIFB project status (kiifb.org). How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project