Thamarassery Varattiakkal Road
Completed100%Physical progress
95.7%Financial progress
Scheduled start10-03-2023
Scheduled completion28-09-2024
- Contractor
- M/s . BAABConstruction(I)Pvt. Ltd
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹11,00,97,608₹11.01 crore
- Amount paid
- ₹10,53,37,854₹10.53 crore
- Paid to contractor
- ₹9,95,56,969₹9.96 crore
- Administrative sanction (AS)
- ₹25,00,00,000₹25 crore
- Financial sanction (FS)
- ₹40,57,31,197₹40.57 crore
- Technical sanction (TS)
- ₹11,00,97,608₹11.01 crore
- Tender amount
- ₹10,11,41,296₹10.11 crore
- Current progress
- DBM completed upto 14.671km in the first stretch .drainage completed.BC to be done. In the second stretch DBM completed (Varattiakkal to CWRDM). BC to be done. Work terminated on 08.04.2022 with risk and cost of contractor.Balance work tendered on 17/6