Kanakkuമലയാളം

Total of works

₹41.5 crore

₹41,50,00,000

Stage

Completed

Status of the works, as KIIFB records it.

Location

Works (1)

Muttungal-Nadapuram-Pakramthalam Road

Completed
100%Physical progress
95.2%Financial progress
Scheduled start15-02-2018
Scheduled completion30-04-2024
Implementing agency (SPV)
KRFB
Contract amount
₹34,88,48,918₹34.88 crore
Amount paid
₹33,19,98,377₹33.2 crore
Paid to contractor
₹30,71,86,114₹30.72 crore
Administrative sanction (AS)
₹30,00,00,000₹30 crore
Financial sanction (FS)
₹41,50,00,000₹41.5 crore
Technical sanction (TS)
₹38,71,24,506₹38.71 crore
Tender amount
₹35,00,21,760₹35 crore
Letter of acceptance (LOA)
₹35,00,21,760₹35 crore
Current progress
Work inaugurated. RE works remaining, but RE is not sanctioned yet. RE placed in the 99th Technical committee held on 04.04.2022 and submitted to KIIFB on 04.05.2022 as per direction of TS committee.Comments from TS committee attented.

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹41,50,00,000₹41.5 crore

Details

Project code
PWD004-26-01
Department
Public Works
Constituency
Nadapuram

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026