Muttungal-Nadapuram-Pakramthalam Road
Completed100%Physical progress
95.2%Financial progress
Scheduled start15-02-2018
Scheduled completion30-04-2024
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹34,88,48,918₹34.88 crore
- Amount paid
- ₹33,19,98,377₹33.2 crore
- Paid to contractor
- ₹30,71,86,114₹30.72 crore
- Administrative sanction (AS)
- ₹30,00,00,000₹30 crore
- Financial sanction (FS)
- ₹41,50,00,000₹41.5 crore
- Technical sanction (TS)
- ₹38,71,24,506₹38.71 crore
- Tender amount
- ₹35,00,21,760₹35 crore
- Letter of acceptance (LOA)
- ₹35,00,21,760₹35 crore
- Current progress
- Work inaugurated. RE works remaining, but RE is not sanctioned yet. RE placed in the 99th Technical committee held on 04.04.2022 and submitted to KIIFB on 04.05.2022 as per direction of TS committee.Comments from TS committee attented.