Total of works

₹423.72 crore

₹4,23,72,00,000

Stage

Approved

Status of the works, as KIIFB records it.

Location

Works (1)

Kannur Airport connectivity package roads

Approved
0%Physical progress
0%Financial progress
Contractor
Not published
Implementing agency (SPV)
KRFB
Contract amount
Not published
Amount paid
Not published
Administrative sanction (AS)
₹50,00,00,000₹50 crore
Financial sanction (FS)
₹4,23,72,00,000₹423.72 crore

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹4,23,72,00,000₹423.72 crore

Details

Project code
PWD004-29
Department
Public Works
Constituency
Dharmadom

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Kannur Airport connectivity package roads
  • Scheduled start and completion dates · Kannur Airport connectivity package roads
  • Amount paid · Kannur Airport connectivity package roads

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256