Arammayil Parapram road
Completed100%Physical progress
97%Financial progress
Scheduled start06-12-2017
Scheduled completion12-06-2023
- Contractor
- M/s . BAABCostruction(I)Pvt. Ltd.
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹12,04,25,446₹12.04 crore
- Amount paid
- ₹11,67,84,007₹11.68 crore
- Paid to contractor
- ₹10,80,25,198₹10.8 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹14,53,00,000₹14.53 crore
- Technical sanction (TS)
- ₹14,53,00,000₹14.53 crore
- Tender amount
- ₹12,04,25,446₹12.04 crore
- Letter of acceptance (LOA)
- ₹12,04,25,446₹12.04 crore
- Current progress
- Work completed.