Mathuvinmel - Kunnikode road
Foreclosed96.2%Physical progress
92.7%Financial progress
Scheduled start13-04-2018
Scheduled completion30-06-2021
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹39,43,96,033₹39.44 crore
- Amount paid
- ₹39,01,98,476₹39.02 crore
- Paid to contractor
- ₹36,08,18,871₹36.08 crore
- Financial sanction (FS)
- ₹43,04,00,000₹43.04 crore
- Technical sanction (TS)
- ₹43,04,00,000₹43.04 crore
- Tender amount
- ₹39,43,96,033₹39.44 crore
- Letter of acceptance (LOA)
- ₹39,43,96,033₹39.44 crore
- Current progress
- BM & BC Completed except 2 junctions to be done(350m). Revised estimate approval pending with KIIFB. The contractor requested to release him of the contract from executing the balance work since variation in cost of material at the time of contract and