Anayadi Pazhakulam Kurampala Keerukuzhi Chandanappally Koodal Road - FDR on pilot phase (km 0/810 to 6/710)- Contract work

Spent on this package so far

₹7.66 crore

₹7,66,19,781

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Contract Process Completed · How we group

Location

Money trail

Estimated amount
₹1,44,41,60,615Estimate of sub-project PWD004-47, shared by 2 contract packages
Expenditure reported · this package
₹7,66,19,781
Expenditure reported · all 2 packages
₹1,08,51,05,21675.1% of the estimated amount

Details

Project code
PWD004-47-01
Department
Public Works

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Improvements of Anayadi - Pazhakulam - Kurampala - Keerukuzhi - Chandnappally - Koodal road”. The figures below are for that whole project, not this package alone.

Approved
₹1,44,41,60,615₹144.42 crore
Paid so far
₹1,25,71,07,99587% of the amount approved

This package

Work started
₹8.34 crorepaid
₹8.37 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress