Anayadi - Pazhakulam road
In progress94.3%Physical progress
91.9%Financial progress
Scheduled start28-05-2019
Scheduled completion30-11-2024
- Contractor
- Metaguard Engineersand Contractors
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹1,15,31,65,675₹115.32 crore
- Amount paid
- ₹1,06,00,60,058₹106.01 crore
- Paid to contractor
- ₹98,23,72,373₹98.24 crore
- Administrative sanction (AS)
- ₹40,00,00,000₹40 crore
- Financial sanction (FS)
- ₹1,44,41,60,615₹144.42 crore
- Technical sanction (TS)
- ₹1,15,31,65,675₹115.32 crore
- Tender amount
- ₹92,96,91,965₹92.97 crore
- Letter of acceptance (LOA)
- ₹92,96,91,965₹92.97 crore
- Current progress
- Total 32km. BM work ongoing, and completed for 24.00 km. WMM work in progress. Construction of culverts, Side protection works ongoing. Drain works ongoing. RE re-submitted after making necessary corrections. BC can be done only after shifting KWA pip