PWD004-47-02 Adoor

Anayadi - Pazhakulam - Kurampala - Keerukuzhi - Chandnappally - Koodal road- Contract Work

Spent on this package so far

₹100.85 crore

₹1,00,84,85,435

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Flags (1)

Overdue · Anayadi - Pazhakulam road

Scheduled completion was 30-11-2024. That was 671 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Anayadi - Pazhakulam road

In progress
94.3%Physical progress
91.9%Financial progress
Scheduled start28-05-2019
Scheduled completion30-11-2024
Implementing agency (SPV)
KRFB
Contract amount
₹1,15,31,65,675₹115.32 crore
Amount paid
₹1,06,00,60,058₹106.01 crore
Paid to contractor
₹98,23,72,373₹98.24 crore
Administrative sanction (AS)
₹40,00,00,000₹40 crore
Financial sanction (FS)
₹1,44,41,60,615₹144.42 crore
Technical sanction (TS)
₹1,15,31,65,675₹115.32 crore
Tender amount
₹92,96,91,965₹92.97 crore
Letter of acceptance (LOA)
₹92,96,91,965₹92.97 crore
Current progress
Total 32km. BM work ongoing, and completed for 24.00 km. WMM work in progress. Construction of culverts, Side protection works ongoing. Drain works ongoing. RE re-submitted after making necessary corrections. BC can be done only after shifting KWA pip

Money trail

Estimated amount
₹1,44,41,60,615Estimate of sub-project PWD004-47, shared by 2 contract packages
Expenditure reported · this package
₹1,00,84,85,435
Expenditure reported · all 2 packages
₹1,08,51,05,21675.1% of the estimated amount

Details

Project code
PWD004-47-02
Department
Public Works
Constituency
Adoor

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Improvements of Anayadi - Pazhakulam - Kurampala - Keerukuzhi - Chandnappally - Koodal road”. The figures below are for that whole project, not this package alone.

Approved
₹1,44,41,60,615₹144.42 crore
Paid so far
₹1,25,71,07,99587% of the amount approved

Source: KIIFB project status (kiifb.org). How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…