Kanakkuമലയാളം
PWD004-52-03 Karunagapally

Developments to Vettamukku - Thevalakkara - Mynagappally - Sasthamcotta - Manappally - Kanjirathummoodu - Thamarakkulam road-BALANCE WORK-CONTRACT

Spent on this package so far

₹7.75 crore

₹7,75,06,143

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Flags (1)

Overdue · Vettamukka-Thevalakkara road

Scheduled completion was 14-06-2025. That was 475 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Vettamukka-Thevalakkara road

In progress
45%Physical progress
21.1%Financial progress
Scheduled start15-06-2024
Scheduled completion14-06-2025
Implementing agency (SPV)
KRFB
Contract amount
₹29,76,96,789₹29.77 crore
Amount paid
₹6,27,85,314₹6.28 crore
Paid to contractor
₹5,87,94,709₹5.88 crore
Administrative sanction (AS)
₹50,00,00,000₹50 crore
Financial sanction (FS)
₹71,18,00,520₹71.18 crore
Technical sanction (TS)
₹27,31,50,000₹27.32 crore
Tender amount
₹29,76,96,789₹29.77 crore
Current progress
DBM work completed. Drain and Culvert construction as per estimate completed. BC and road safety work are to be done. Based on the judgement on the petition filed by the contractor before the Hon' ble High court andas per the direction of KIIFB,the work

Money trail

Estimated amount
₹71,18,00,520Estimate of sub-project PWD004-52, shared by 2 contract packages
Expenditure reported · this package
₹7,75,06,143
Expenditure reported · all 2 packages
₹46,23,02,45664.9% of the estimated amount

Details

Project code
PWD004-52-03
Department
Public Works
Constituency
Karunagapally

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Developments to Vettamukku - Thevalakkara - Mynagappally - Sasthamcotta - Manappally - Kanjirathummoodu - Thamarakkulam road”. The figures below are for that whole project, not this package alone.

Approved
₹71,18,00,520₹71.18 crore
Paid so far
₹1,68,94,35,885₹168.94 crore

Source: KIIFB project status (kiifb.org). How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project