Vettamukka-Thevalakkara road
In progress45%Physical progress
21.1%Financial progress
Scheduled start15-06-2024
Scheduled completion14-06-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹29,76,96,789₹29.77 crore
- Amount paid
- ₹6,27,85,314₹6.28 crore
- Paid to contractor
- ₹5,87,94,709₹5.88 crore
- Administrative sanction (AS)
- ₹50,00,00,000₹50 crore
- Financial sanction (FS)
- ₹71,18,00,520₹71.18 crore
- Technical sanction (TS)
- ₹27,31,50,000₹27.32 crore
- Tender amount
- ₹29,76,96,789₹29.77 crore
- Current progress
- DBM work completed. Drain and Culvert construction as per estimate completed. BC and road safety work are to be done. Based on the judgement on the petition filed by the contractor before the Hon' ble High court andas per the direction of KIIFB,the work