Ayathil-Pallimukku Road
Completed100%Physical progress
100%Financial progress
Scheduled start19-06-2018
Scheduled completion16-11-2021
- Contractor
- Robin P. Alex
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹9,93,63,994₹9.94 crore
- Amount paid
- ₹9,93,63,994₹9.94 crore
- Paid to contractor
- ₹9,32,31,168₹9.32 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹10,81,30,000₹10.81 crore
- Technical sanction (TS)
- ₹10,75,00,000₹10.75 crore
- Tender amount
- ₹11,16,35,557₹11.16 crore
- Letter of acceptance (LOA)
- ₹11,16,35,557₹11.16 crore
- Current progress
- WORK COMPLETED