Venjaramood Ring Road
Completed100%Physical progress
94.2%Financial progress
Scheduled start05-02-2018
Scheduled completion18-11-2023
- Contractor
- Nizamudeen
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹22,67,02,456₹22.67 crore
- Amount paid
- ₹21,34,95,654₹21.35 crore
- Paid to contractor
- ₹19,75,33,308₹19.75 crore
- Financial sanction (FS)
- ₹39,63,24,327₹39.63 crore
- Technical sanction (TS)
- ₹42,82,906₹42.83 lakh
- Tender amount
- ₹22,67,02,456₹22.67 crore
- Letter of acceptance (LOA)
- ₹22,67,02,456₹22.67 crore
- Current progress
- Outer ring road - 90% work completed, BC for 3km to be done. Inner ring road - 11(1) published. 4.7Cr remitted to LA Thahasildar. Valuation details taken from field and reports under preparation. Purambokke area correction submitted to Collector for ap