Kallupalam-Eravipuram- Mayanad road
Terminated30%Physical progress
85.9%Financial progress
Scheduled start14-05-2018
Scheduled completion13-05-2019
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹23,35,09,709₹23.35 crore
- Amount paid
- ₹7,31,69,380₹7.32 crore
- Paid to contractor
- ₹6,76,81,675₹6.77 crore
- Administrative sanction (AS)
- ₹25,00,00,000₹25 crore
- Financial sanction (FS)
- ₹29,45,02,351₹29.45 crore
- Technical sanction (TS)
- ₹23,91,00,000₹23.91 crore
- Tender amount
- ₹23,35,09,709₹23.35 crore
- Letter of acceptance (LOA)
- ₹23,35,09,709₹23.35 crore
- Current progress
- DBM for a length of 6.738 km completed. 6 new cross drains constructed and widening of 2 cross drains done. Gabion retaining wall for a length of 71m completed. The work was in a standstill position for a long period and the contractor was finally direc