Alamcode Anjuthengu Muthalapozhi Road
In progress85%Physical progress
56%Financial progress
Scheduled start22-10-2020
Scheduled completion30-09-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹35,46,14,635₹35.46 crore
- Amount paid
- ₹19,85,65,267₹19.86 crore
- Paid to contractor
- ₹18,19,04,500₹18.19 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹47,11,29,282₹47.11 crore
- Technical sanction (TS)
- ₹98,29,667₹98.3 lakh
- Tender amount
- ₹36,94,17,914₹36.94 crore
- Letter of acceptance (LOA)
- ₹32,98,37,423₹32.98 crore
- Current progress
- Work progress 24%. Culvert - 12/14 completed. Cross ducts - 17/19 completed Drain - 4568/7000 m casted, 3429/7000 m placed LIme stabilisation - 19% , up to 1/520 done. GSB 18%, WMM - 15% Extension of TOC requested upto 20.9.2022 Utility shifting work