Total of works

₹47.11 crore

₹47,11,29,282

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Alamcode Anjuthengu Muthalapozhi Road

Scheduled completion was 30-09-2025. That was 367 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Alamcode Anjuthengu Muthalapozhi Road

In progress
85%Physical progress
56%Financial progress
Scheduled start22-10-2020
Scheduled completion30-09-2025
Implementing agency (SPV)
KRFB
Contract amount
₹35,46,14,635₹35.46 crore
Amount paid
₹19,85,65,267₹19.86 crore
Paid to contractor
₹18,19,04,500₹18.19 crore
Administrative sanction (AS)
₹10,00,00,000₹10 crore
Financial sanction (FS)
₹47,11,29,282₹47.11 crore
Technical sanction (TS)
₹98,29,667₹98.3 lakh
Tender amount
₹36,94,17,914₹36.94 crore
Letter of acceptance (LOA)
₹32,98,37,423₹32.98 crore
Current progress
Work progress 24%. Culvert - 12/14 completed. Cross ducts - 17/19 completed Drain - 4568/7000 m casted, 3429/7000 m placed LIme stabilisation - 19% , up to 1/520 done. GSB 18%, WMM - 15% Extension of TOC requested upto 20.9.2022 Utility shifting work

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹47,11,29,282₹47.11 crore

Details

Project code
PWD004-72-01
Department
Public Works
Constituency
Attingal,Chirayinkeezhu

What we don't know yet

The dashboard publishes every field we check.