Shivagiri Ring road
Completed100%Physical progress
94.6%Financial progress
Scheduled start09-11-2018
Scheduled completion31-10-2021
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹13,63,84,940₹13.64 crore
- Amount paid
- ₹12,90,01,545₹12.9 crore
- Paid to contractor
- ₹11,93,17,625₹11.93 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹13,75,00,000₹13.75 crore
- Technical sanction (TS)
- ₹13,75,00,000₹13.75 crore
- Tender amount
- ₹13,63,84,940₹13.64 crore
- Letter of acceptance (LOA)
- ₹13,63,84,940₹13.64 crore
- Current progress
- Work completed and board installed by Roads wing