Muthalapozhy- Paripally Road
Completed100%Physical progress
84.4%Financial progress
Scheduled start22-10-2020
Scheduled completion31-10-2025
- Contractor
- Thajudheen A
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹40,94,81,290₹40.95 crore
- Amount paid
- ₹34,56,36,165₹34.56 crore
- Paid to contractor
- ₹32,64,82,137₹32.65 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹47,53,60,468₹47.54 crore
- Technical sanction (TS)
- ₹40,94,81,291₹40.95 crore
- Tender amount
- ₹36,36,87,445₹36.37 crore
- Letter of acceptance (LOA)
- ₹32,47,20,933₹32.47 crore
- Current progress
- Work progress 16%. Culvert - 75%, 6/8 done, cross ducts - 72%, 10/14 done Drain - 2700/8500 m done, Retaining wall construction started. Road widening started, GSB - 19% & WMM - 18% 60% evicition completed. KSEB utility shifting progressing. KWA work te