Palode Brimore Road
Completed100%Physical progress
96.4%Financial progress
Scheduled start27-02-2018
Scheduled completion30-06-2021
- Contractor
- M/s Sreedhanya Construction Company
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹44,92,91,893₹44.93 crore
- Amount paid
- ₹43,32,30,740₹43.32 crore
- Paid to contractor
- ₹40,14,90,069₹40.15 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹49,69,00,000₹49.69 crore
- Technical sanction (TS)
- ₹46,09,87,961₹46.1 crore
- Tender amount
- ₹45,69,05,108₹45.69 crore
- Letter of acceptance (LOA)
- ₹45,69,05,108₹45.69 crore
- Current progress
- Work completed and board installed by Roads wing