Chandrapura - Pariyaram Medical College Road
Completed100%Physical progress
98.9%Financial progress
Scheduled start27-11-2018
Scheduled completion23-10-2023
- Contractor
- M/s K. K. Builders
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹35,90,23,545₹35.9 crore
- Amount paid
- ₹35,52,05,544₹35.52 crore
- Paid to contractor
- ₹32,92,41,948₹32.92 crore
- Administrative sanction (AS)
- ₹25,00,00,000₹25 crore
- Financial sanction (FS)
- ₹44,70,29,570₹44.7 crore
- Technical sanction (TS)
- ₹38,65,00,000₹38.65 crore
- Tender amount
- ₹35,90,23,943₹35.9 crore
- Letter of acceptance (LOA)
- ₹35,90,23,943₹35.9 crore
- Current progress
- DBM & BC completed. Traffic safety works nearing completion. All drainage and side protection works in Vellikkeel Ozhakrom reach is in progress at chainages where the land is available (free surrender).Installation of sign board work completed.