Total of works

₹44.7 crore

₹44,70,29,570

Stage

Completed

Status of the works, as KIIFB records it.

Location

Works (1)

Chandrapura - Pariyaram Medical College Road

Completed
100%Physical progress
98.9%Financial progress
Scheduled start27-11-2018
Scheduled completion23-10-2023
Implementing agency (SPV)
KRFB
Contract amount
₹35,90,23,545₹35.9 crore
Amount paid
₹35,52,05,544₹35.52 crore
Paid to contractor
₹32,92,41,948₹32.92 crore
Administrative sanction (AS)
₹25,00,00,000₹25 crore
Financial sanction (FS)
₹44,70,29,570₹44.7 crore
Technical sanction (TS)
₹38,65,00,000₹38.65 crore
Tender amount
₹35,90,23,943₹35.9 crore
Letter of acceptance (LOA)
₹35,90,23,943₹35.9 crore
Current progress
DBM & BC completed. Traffic safety works nearing completion. All drainage and side protection works in Vellikkeel Ozhakrom reach is in progress at chainages where the land is available (free surrender).Installation of sign board work completed.

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹44,70,29,570₹44.7 crore

Details

Project code
PWD004-89-01
Department
Public Works
Constituency
Kalliasseri,Taliparamba

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026