Tirur - Kadalundi Road
Completed100%Physical progress
96%Financial progress
Scheduled start10-10-2018
Scheduled completion31-05-2023
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹59,42,03,308₹59.42 crore
- Amount paid
- ₹57,01,70,703₹57.02 crore
- Paid to contractor
- ₹52,46,87,760₹52.47 crore
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹61,17,00,000₹61.17 crore
- Technical sanction (TS)
- ₹61,32,57,202₹61.33 crore
- Tender amount
- ₹57,72,85,443₹57.73 crore
- Letter of acceptance (LOA)
- ₹57,72,85,443₹57.73 crore
- Current progress
- Drain- 100%, Utility Duct- 100%, Culverts- 100% Cross Duct- 100%, GSB- 100% WMM- 100%, DBM- 100%, BC- 100% Retaining wall at pond side pending. RE sanctioned by KIIFB. Supplemental agreement executed