Kanakkuമലയാളം

Total of works

₹291.63 crore

₹2,91,63,00,000

Stage

Approved

Status of the works, as KIIFB records it.

Location

Works (1)

Airport Link- Chorakkala- Bavupparamba- Road

Approved
0%Physical progress
Not publishedFinancial progress
Contractor
Not published
Implementing agency (SPV)
KRFB
Contract amount
Not published
Amount paid
Not published
Administrative sanction (AS)
₹47,00,00,000₹47 crore
Financial sanction (FS)
₹2,91,63,00,000₹291.63 crore
Technical sanction (TS)
₹1,88,51,69,841₹188.52 crore
Current progress
Revenue AS for LA obtained on 08-09-21 vide GO(Rt)3014/2021/RD- Joint inspection with Revenue team completed- Design review process by KIIFB is in progress- TS estimate submitted on 23-11-2021.Contingency charge remitted to Revenue Department- LA in pr

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹2,91,63,00,000₹291.63 crore

Details

Project code
PWD004-94-02
Department
Public Works
Constituency
Taliparamba,Mattannur

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Airport Link- Chorakkala- Bavupparamba- Road
  • Scheduled start and completion dates · Airport Link- Chorakkala- Bavupparamba- Road
  • Amount paid · Airport Link- Chorakkala- Bavupparamba- Road

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…