Cherupuzha - Muthuvam Road
Completed100%Physical progress
97.9%Financial progress
Scheduled start22-06-2018
Scheduled completion13-11-2025
- Contractor
- M/s Irikkur Construction Company
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹19,78,57,172₹19.79 crore
- Amount paid
- ₹19,36,52,569₹19.37 crore
- Paid to contractor
- ₹17,91,28,621₹17.91 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹23,69,00,000₹23.69 crore
- Technical sanction (TS)
- ₹23,69,00,000₹23.69 crore
- Tender amount
- ₹19,88,97,119₹19.89 crore
- Letter of acceptance (LOA)
- ₹19,88,97,119₹19.89 crore
- Current progress
- Completed