Punnakadavu - Ezhilode Road
Approved100%Physical progress
Not publishedFinancial progress
Scheduled start28-09-2025
Scheduled completion27-03-2026
- Contractor
- Not published
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹6,68,26,870₹6.68 crore
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹17,23,00,000₹17.23 crore
- Technical sanction (TS)
- ₹6,89,64,782₹6.9 crore
- Tender amount
- ₹6,68,26,870₹6.68 crore
- Current progress
- 55% completed, 3.6 km mss completed(coastal highway portion), 0/000 to 3/220 DBM completed, The land has been assured by MLA,Panchayath President and Block members, for widening of RoW. M/s P K Sulphiker LLP has decided to continue with the work. Agreem