Kadungallur - Vilayil - Chaliyapuram Road
Completed100%Physical progress
98.7%Financial progress
Scheduled start01-10-2018
Scheduled completion31-05-2022
- Contractor
- M/s PMRConstruction Company
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹15,33,24,111₹15.33 crore
- Amount paid
- ₹15,13,41,851₹15.13 crore
- Paid to contractor
- ₹14,01,51,303₹14.02 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹16,41,00,000₹16.41 crore
- Technical sanction (TS)
- ₹17,50,78,217₹17.51 crore
- Tender amount
- ₹13,52,14,206₹13.52 crore
- Letter of acceptance (LOA)
- ₹13,52,14,206₹13.52 crore
- Current progress
- Whole Work completed, Work Inaguarated by Hon. PWD Minister Sri G Sudhakaran through video conference on 29/06/2020. Revised Estimate submitted to KRFB and 66 th KRFB Technical committee approved. The committee forward the RE to KIIFB for approval. f