10 Rob's
In progress82%Physical progress
91.6%Financial progress
Scheduled start11-01-2021
Scheduled completion31-08-2025
- Contractor
- SPLInfrastructure Private Limited
- Implementing agency (SPV)
- RBDCK
- Contract amount
- ₹2,43,10,22,505₹243.1 crore
- Amount paid
- ₹2,22,67,50,516₹222.68 crore
- Paid to contractor
- ₹1,93,61,95,524₹193.62 crore
- Financial sanction (FS)
- ₹2,96,51,79,404₹296.52 crore
- Technical sanction (TS)
- ₹2,43,10,22,505₹243.1 crore
- Tender amount
- ₹2,81,65,90,280₹281.66 crore
- Letter of acceptance (LOA)
- ₹2,81,65,90,280₹281.66 crore
- Current progress
- Construction works in progress except at Chelari-Chettippadi ROB. Detailed project status given separately.