Chelari- Chettippadi ROB
In progress27.6%Physical progress
28.9%Financial progress
Scheduled start14-08-2024
Scheduled completion24-12-2025
- Implementing agency (SPV)
- RBDCK
- Contract amount
- ₹31,88,88,038₹31.89 crore
- Amount paid
- ₹9,21,31,032₹9.21 crore
- Paid to contractor
- ₹8,62,75,245₹8.63 crore
- Financial sanction (FS)
- ₹2,96,51,79,404₹296.52 crore
- Technical sanction (TS)
- ₹29,01,55,867₹29.02 crore
- Tender amount
- ₹31,88,88,038₹31.89 crore
- Current progress
- Demolition of structures & tree cutting works were completed. Construction works not yet started. The project comes under the alignment of Semi High Speed Rail project. Alignment and GADs are modified as suggested by KRDCL and submitted to KRDCL. GAD ap