Total of works

₹12.03 crore

₹12,02,76,081

Stage

Approved

Status of the works, as KIIFB records it.

Location

Flags (1)

Payment ahead of progress · Maliyaekal Rail Bridge

Reported financial progress is 100% and reported physical progress is 0%, a gap of 100 points.

Rule: Reported financial progress is 25 or more percentage points ahead of reported physical progress. Rule version 2 · Since 30-09-2026

Works (1)

Maliyaekal Rail Bridge

Approved
0%Physical progress
100%Financial progress
Contractor
Not published
Implementing agency (SPV)
RBDCK
Contract amount
Not published
Amount paid
₹19,00,000₹19 lakh
Administrative sanction (AS)
₹25,00,00,000₹25 crore
Financial sanction (FS)
₹12,02,76,081₹12.03 crore
Current progress
Utility Shifting charges received from KIIFB and the same was released to the agencies on 18.08.2021. Shifting in progress.

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹12,02,76,081₹12.03 crore

Details

Project code
PWD005-08
Department
Public Works
Constituency
Karunagappally

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Maliyaekal Rail Bridge
  • Scheduled start and completion dates · Maliyaekal Rail Bridge