Vaduthala ROB
Approved0%Physical progress
Not publishedFinancial progress
- Contractor
- Not published
- Implementing agency (SPV)
- RBDCK
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹35,00,00,000₹35 crore
- Financial sanction (FS)
- ₹91,90,00,000₹91.9 crore
- Technical sanction (TS)
- ₹20,48,69,122₹20.49 crore
- Tender amount
- ₹22,18,99,000₹22.19 crore
- Letter of acceptance (LOA)
- ₹18,80,50,000₹18.81 crore
- Current progress
- LA requisition submitted to Dt. Collector Ernakulam on 23.08.2017. GAD approved on 29.01.2021. Stone planting completed and letter send to District Collector for joint site inspection. District Collector informed that the LA procedure expired (denova) du