Kallanthode Koolimaud Road
In progress78%Physical progress
61.6%Financial progress
Scheduled start09-05-2023
Scheduled completion31-12-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹38,37,89,177₹38.38 crore
- Amount paid
- ₹23,77,77,616₹23.78 crore
- Paid to contractor
- ₹22,26,64,563₹22.27 crore
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹42,30,06,824₹42.3 crore
- Technical sanction (TS)
- ₹39,48,65,327₹39.49 crore
- Tender amount
- ₹38,57,10,382₹38.57 crore
- Current progress
- Work Terminated on 17/7/2020 without risk & cost of contractor. Revised FS obtained for Rs.42,30,06,824. Balance work tendered on 24/6/2022 and technical bid opening date is 11/7/2022. Tender under process.Temporary maintenance work completed .