Cherunniyoor- Ottoor Road
Completed100%Physical progress
97.8%Financial progress
Scheduled start25-06-2018
Scheduled completion28-02-2022
- Contractor
- Thajudeen A
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹28,23,19,205₹28.23 crore
- Amount paid
- ₹27,60,47,297₹27.6 crore
- Paid to contractor
- ₹25,75,25,428₹25.75 crore
- Financial sanction (FS)
- ₹32,34,00,000₹32.34 crore
- Technical sanction (TS)
- ₹32,34,00,000₹32.34 crore
- Tender amount
- ₹28,23,19,205₹28.23 crore
- Letter of acceptance (LOA)
- ₹28,23,19,205₹28.23 crore
- Current progress
- Work completed and board installed by Roads wing