Ulikkal - Thermala - Kanhilery - Kaniyar Vayal Road
Completed100%Physical progress
98.1%Financial progress
Scheduled start30-10-2018
Scheduled completion28-10-2023
- Contractor
- M/s . Ernad Engineering Enterprises
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹55,16,97,887₹55.17 crore
- Amount paid
- ₹54,12,02,556₹54.12 crore
- Paid to contractor
- ₹50,05,76,311₹50.06 crore
- Financial sanction (FS)
- ₹61,27,00,000₹61.27 crore
- Technical sanction (TS)
- ₹55,16,97,888₹55.17 crore
- Tender amount
- ₹54,32,84,740₹54.33 crore
- Letter of acceptance (LOA)
- ₹54,32,84,740₹54.33 crore
- Current progress
- 94% completed- GSB,WMM laying work 18 km completed. DBM and BC completed.Drainage, side protection and road safety works are in progress.