Kattampalli Kadavu- Thadikkadavu Road
Completed100%Physical progress
93.9%Financial progress
Scheduled start08-03-2019
Scheduled completion11-04-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹71,12,16,257₹71.12 crore
- Amount paid
- ₹66,77,71,730₹66.78 crore
- Paid to contractor
- ₹61,76,88,818₹61.77 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹72,16,07,340₹72.16 crore
- Technical sanction (TS)
- ₹2,47,55,945₹2.48 crore
- Tender amount
- ₹71,12,16,257₹71.12 crore
- Letter of acceptance (LOA)
- ₹71,12,16,257₹71.12 crore
- Current progress
- 93% completed. DBM work completed. BC completed except at chainage 10/00 to11/850 where utility shifting of KSEB has to be completed. Road furniture works completed. The work can be completed only after Utility shifting of KSEB .KSEB utility shifting(33