Chathan Master Road
Approved0%Physical progress
0%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- KRFB
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹34,36,92,797₹34.37 crore
- Current progress
- FS obtained.Part TS for planting boundary stone accorded and work arranged for plating Bounadary stones and fixing new alignment and to prepare necessary drawings. Encroachment survey is not completed by survey Dept. Work is shortlisted in FDR category.