Work 1
In progress79.1%Physical progress
66.2%Financial progress
Scheduled start06-01-2022
Scheduled completion07-03-2026
- Contractor
- KKBuilders
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹47,80,62,715₹47.81 crore
- Amount paid
- ₹27,89,74,927₹27.9 crore
- Paid to contractor
- ₹26,12,05,525₹26.12 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹52,78,92,000₹52.79 crore
- Technical sanction (TS)
- ₹52,78,92,000₹52.79 crore
- Tender amount
- ₹42,13,24,698₹42.13 crore
- Letter of acceptance (LOA)
- ₹37,61,82,766₹37.62 crore
- Current progress
- Work awarded to M/s. K.K. Builders and Agreement executed on 06.01.2022. Work started. Drain work,DR work and Culvert work in progress.