Thottilpalam Kunduthode road
Completed100%Physical progress
88.8%Financial progress
Scheduled start24-02-2022
Scheduled completion23-08-2023
- Contractor
- BAABConstructions(I)Pvt Ltd
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹13,73,20,224₹13.73 crore
- Amount paid
- ₹12,19,51,851₹12.2 crore
- Paid to contractor
- ₹11,41,62,246₹11.42 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹29,59,43,540₹29.59 crore
- Technical sanction (TS)
- ₹14,75,00,000₹14.75 crore
- Tender amount
- ₹13,73,20,224₹13.73 crore
- Letter of acceptance (LOA)
- ₹12,26,07,343₹12.26 crore
- Current progress
- Work awarded to M/s. BAAB Construction and Agreement executed on 20.11.2021. Work started. Drain and Culvert work in progress.