Perumbavoor Bypass
In progress25%Physical progress
9.5%Financial progress
Scheduled start06-06-2024
Scheduled completion05-12-2025
- Contractor
- Rajeshmathewandcompany
- Implementing agency (SPV)
- RBDCK
- Contract amount
- ₹29,54,65,590₹29.55 crore
- Amount paid
- ₹2,80,06,352₹2.8 crore
- Paid to contractor
- ₹2,62,26,287₹2.62 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹3,01,71,99,751₹301.72 crore
- Technical sanction (TS)
- ₹26,86,05,337₹26.86 crore
- Tender amount
- ₹29,54,65,590₹29.55 crore
- Letter of acceptance (LOA)
- ₹25,03,94,568₹25.04 crore
- Current progress
- LA requisition submitted to Dt. Collector Ernakulam on 22.02.2018. KIIFB has approved to execute the projects in two phases. Phase I (CH 2.730km to CH 3.760km): 11(1) notification published on 12.08.2020. Land survey completed and SD records were appro