PWD008-02-03 Kottarakkara

Construction of 11 Bridges

Total of works

₹14.7 crore

₹14,70,05,895

Stage

Completed

Status of the works, as KIIFB records it.

Location

Works (1)

Arakakadavu Bridge

Completed
100%Physical progress
68.7%Financial progress
Scheduled start02-08-2023
Scheduled completion28-10-2025
Contractor
M/s Robin PAlex
Implementing agency (SPV)
KRFB
Contract amount
₹12,47,42,613₹12.47 crore
Amount paid
₹8,56,47,440₹8.56 crore
Paid to contractor
₹8,09,29,545₹8.09 crore
Administrative sanction (AS)
₹10,00,00,000₹10 crore
Financial sanction (FS)
₹14,70,05,895₹14.7 crore
Technical sanction (TS)
₹10,55,65,166₹10.56 crore
Tender amount
₹12,88,46,927₹12.88 crore
Current progress
Bridge proper completed. Later work terminated without the risk and cost of the contractor. Balance work of Approach Road and allied works Tendered and awaiting tender sanction

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹14,70,05,895₹14.7 crore

Details

Project code
PWD008-02-03
Department
Public Works
Constituency
Kottarakkara

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…