Total of works

₹10.24 crore

₹10,24,00,000

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (2)

Payment ahead of progress · Sreedhari Bridge

Reported financial progress is 40.8% and reported physical progress is 15%, a gap of 25.8 points.

Rule: Reported financial progress is 25 or more percentage points ahead of reported physical progress. Rule version 2 · Since 30-09-2026

Overdue · Sreedhari Bridge

Scheduled completion was 08-09-2025. That was 389 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Sreedhari Bridge

In progress
15%Physical progress
40.8%Financial progress
Scheduled start08-04-2025
Scheduled completion08-09-2025
Implementing agency (SPV)
KRFB
Contract amount
₹3,84,88,021₹3.85 crore
Amount paid
₹1,57,09,249₹1.57 crore
Paid to contractor
₹1,47,10,779₹1.47 crore
Administrative sanction (AS)
₹10,00,00,000₹10 crore
Financial sanction (FS)
₹10,24,00,000₹10.24 crore
Technical sanction (TS)
₹3,77,30,000₹3.77 crore
Tender amount
₹3,84,88,021₹3.85 crore
Current progress
LA Details - LA in progress with 11(1) notification published. Details for Final LA amount received from Spl. Tahsildar LA-KIIFB on 31.05.2022 and the same submitted to PD,KRFB on 02.06.2022. Fund approved and transferred to Special Tahsildar LA-KIIFB on

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹10,24,00,000₹10.24 crore

Details

Project code
PWD008-04-06
Department
Public Works
Constituency
Ollur

What we don't know yet