Flyover at Kundanoor
Completed100%Physical progress
99.2%Financial progress
Scheduled start12-03-2018
Scheduled completion01-11-2021
- Contractor
- Sibucherian
- Implementing agency (SPV)
- RBDCK
- Contract amount
- ₹82,64,91,818₹82.65 crore
- Amount paid
- ₹82,00,31,280₹82 crore
- Paid to contractor
- ₹75,52,16,731₹75.52 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹82,74,00,000₹82.74 crore
- Technical sanction (TS)
- ₹84,27,11,882₹84.27 crore
- Tender amount
- ₹74,45,13,845₹74.45 crore
- Letter of acceptance (LOA)
- ₹74,45,13,845₹74.45 crore
- Current progress
- Opened to traffic on 09.01.2021.