Total of works

₹10.82 crore

₹10,81,55,834

Stage

Approved

Status of the works, as KIIFB records it.

Location

Flags (1)

Payment ahead of progress · Eravipuram ROB

Reported financial progress is 97.9% and reported physical progress is 0%, a gap of 97.9 points.

Rule: Reported financial progress is 25 or more percentage points ahead of reported physical progress. Rule version 2 · Since 30-09-2026

Works (1)

Eravipuram ROB

Approved
0%Physical progress
97.9%Financial progress
Contractor
Not published
Implementing agency (SPV)
RBDCK
Contract amount
Not published
Amount paid
₹20,00,000₹20 lakh
Administrative sanction (AS)
₹40,49,00,000₹40.49 crore
Financial sanction (FS)
₹10,81,55,834₹10.82 crore
Current progress
LA completed.

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹10,81,55,834₹10.82 crore

Details

Project code
PWD010-02
Department
Public Works
Constituency
Eravipuram

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Eravipuram ROB
  • Scheduled start and completion dates · Eravipuram ROB

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026