Koduvally ROB
Completed100%Physical progress
100%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- RBDCK
- Contract amount
- Not published
- Amount paid
- ₹14,84,625₹14.85 lakh
- Administrative sanction (AS)
- ₹37,38,00,000₹37.38 crore
- Financial sanction (FS)
- ₹16,31,02,518₹16.31 crore
- Current progress
- Piling works completed (Excluding railway portion). 09/10 Pile caps completed. 06/08 Pier and pier cap completed. Fabrication of 2 Pier and Pier cap is in progress at Fabrication yard. Fabrication of Girders (16 nos) for 4 sapn is in progress at fabric