Kanakkuമലയാളം

Total of works

₹37.83 crore

₹37,83,23,807

Stage

Approved

Status of the works, as KIIFB records it.

Location

Works (1)

Chungam Gate ROB

Approved
0%Physical progress
0%Financial progress
Contractor
Not published
Implementing agency (SPV)
RBDCK
Contract amount
Not published
Amount paid
Not published
Administrative sanction (AS)
₹8,78,00,00,000₹878 crore
Financial sanction (FS)
₹37,83,23,807₹37.83 crore
Current progress
LA plan under preparation. Requisition will be submitted to District Collector after the approval of GAD from Railways. KRDCL informed that the project comes under the alignment of Semi High Speed Rail project & required revision as per modifications s

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹37,83,23,807₹37.83 crore

Details

Project code
PWD011-06
Department
Public Works
Constituency
Kozhikode South

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Chungam Gate ROB
  • Scheduled start and completion dates · Chungam Gate ROB
  • Amount paid · Chungam Gate ROB

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…