Kozhikkal ROB
Approved0%Physical progress
0%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- RBDCK
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹8,78,00,00,000₹878 crore
- Financial sanction (FS)
- ₹46,56,83,000₹46.57 crore
- Current progress
- LA to be taken up after getting approval of GAD from railways. In CMT meeting, Thalassery MLA opined that as an underpass is already constructed, there is no need to construct an ROB as it involves acquisition of large number of structures. RBDCK sent le