SN College Gate ROB
Approved0%Physical progress
0%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- RBDCK
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹8,78,00,00,000₹878 crore
- Financial sanction (FS)
- ₹44,65,82,000₹44.66 crore
- Current progress
- LA to be taken up after getting approval of GAD from railways. GAD was 1st submitted to Railways on 02.03.2019. After several revisions, Revised GAD was submitted to Railways on 09.11.2021 and Railways returned the same for corrections and NOC from NH a