Mynagappally ROB
Approved0%Physical progress
0%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- RBDCK
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹8,78,00,00,000₹878 crore
- Financial sanction (FS)
- ₹49,94,72,710₹49.95 crore
- Current progress
- DPR approved by KIIFB on 26.02.2021. Final GAD submitted to Railways on 23.03.2022. GAD approved by Railways on 12.07.2022. Letter sent to consultant for submission of LA plan and Sketch on 14.07.2022. LA plan is under preparation.