Total of works

₹84.61 crore

₹84,61,00,000

Stage

Approved

Status of the works, as KIIFB records it.

Location

Flags (1)

Payment ahead of progress · Flyover at Pattom

Reported financial progress is 56% and reported physical progress is 0%, a gap of 56 points.

Rule: Reported financial progress is 25 or more percentage points ahead of reported physical progress. Rule version 2 · Since 30-09-2026

Works (1)

Flyover at Pattom

Approved
0%Physical progress
56%Financial progress
Contractor
Not published
Implementing agency (SPV)
KRTL
Contract amount
Not published
Amount paid
₹16,47,00,000₹16.47 crore
Administrative sanction (AS)
₹2,72,84,00,000₹272.84 crore
Financial sanction (FS)
₹84,61,00,000₹84.61 crore
Current progress
11(1) Notification Pubished vide Gazette No. 641 dt.10-2-2021.19(1) published vide Gazette No.831 dated: 15.03.2022. BVR approved on 16.07.2022. Valuation of structures in progress.

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹84,61,00,000₹84.61 crore

Details

Project code
PWD012-02
Department
Public Works
Executing agency
KRTL
Constituency
Vattiyoorkavu

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Flyover at Pattom
  • Scheduled start and completion dates · Flyover at Pattom

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026