PWD012-03-05 Kazhakoottam

Trivandrum / Kozhikode Light Metro Project

Total of works

₹168.68 crore

₹1,68,68,02,675

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Flyover at Sreekariyam

Scheduled completion was 21-07-2026. That was 73 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Flyover at Sreekariyam

In progress
5%Physical progress
4.7%Financial progress
Scheduled start22-01-2025
Scheduled completion21-07-2026
Implementing agency (SPV)
KMRL
Contract amount
₹71,38,04,405₹71.38 crore
Amount paid
₹3,33,44,442₹3.33 crore
Paid to contractor
₹3,12,84,161₹3.13 crore
Administrative sanction (AS)
₹2,72,84,00,000₹272.84 crore
Financial sanction (FS)
₹1,68,68,02,675₹168.68 crore
Technical sanction (TS)
₹61,26,59,638₹61.27 crore
Tender amount
₹71,38,04,405₹71.38 crore
Letter of acceptance (LOA)
₹71,38,04,405₹71.38 crore
Current progress
Passing of awards completed. 80% of total land required (1.0629 Ha out of 1.3277 Ha) taken into possession as on 29.06.2022. Taking possession of remaining land expected to be completed by 15.07.2022. Tender for demolition of first lot of structures in t

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹1,68,68,02,675₹168.68 crore

Details

Project code
PWD012-03-05
Department
Public Works
Constituency
Kazhakoottam

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…