Flyover at Sreekariyam
In progress5%Physical progress
4.7%Financial progress
Scheduled start22-01-2025
Scheduled completion21-07-2026
- Implementing agency (SPV)
- KMRL
- Contract amount
- ₹71,38,04,405₹71.38 crore
- Amount paid
- ₹3,33,44,442₹3.33 crore
- Paid to contractor
- ₹3,12,84,161₹3.13 crore
- Administrative sanction (AS)
- ₹2,72,84,00,000₹272.84 crore
- Financial sanction (FS)
- ₹1,68,68,02,675₹168.68 crore
- Technical sanction (TS)
- ₹61,26,59,638₹61.27 crore
- Tender amount
- ₹71,38,04,405₹71.38 crore
- Letter of acceptance (LOA)
- ₹71,38,04,405₹71.38 crore
- Current progress
- Passing of awards completed. 80% of total land required (1.0629 Ha out of 1.3277 Ha) taken into possession as on 29.06.2022. Taking possession of remaining land expected to be completed by 15.07.2022. Tender for demolition of first lot of structures in t