Kanakkuമലയാളം

Total of works

₹110.67 crore

₹1,10,66,73,950

Stage

Approved

Status of the works, as KIIFB records it.

Location

Flags (1)

Payment ahead of progress · Pullavai to Thottilpalam

Reported financial progress is 76.3% and reported physical progress is 0%, a gap of 76.3 points.

Rule: Reported financial progress is 25 or more percentage points ahead of reported physical progress. Rule version 2 · Since 30-09-2026

Works (1)

Pullavai to Thottilpalam

Approved
0%Physical progress
76.3%Financial progress
Contractor
Not published
Implementing agency (SPV)
KRFB
Contract amount
₹49,17,00,000₹49.17 crore
Amount paid
₹37,54,00,000₹37.54 crore
Paid to contractor
₹35,14,00,000₹35.14 crore
Administrative sanction (AS)
₹35,00,00,00,000₹3,500 crore
Financial sanction (FS)
₹1,10,66,73,950₹110.67 crore
Technical sanction (TS)
₹49,22,00,000₹49.22 crore
Tender amount
₹49,17,00,000₹49.17 crore
Current progress
TS issued once. But TS file is now under scrutiny in PFMS by KIIFB

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹1,10,66,73,950₹110.67 crore

Details

Project code
PWD013-06
Department
Public Works
Constituency
Nadapuram

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Pullavai to Thottilpalam
  • Scheduled start and completion dates · Pullavai to Thottilpalam

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…