Pullavai to Thottilpalam
In progress99.2%Physical progress
91.6%Financial progress
Scheduled start02-04-2022
Scheduled completion31-08-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹51,66,63,279₹51.67 crore
- Amount paid
- ₹47,30,67,448₹47.31 crore
- Paid to contractor
- ₹44,29,12,158₹44.29 crore
- Administrative sanction (AS)
- ₹35,00,00,00,000₹3,500 crore
- Financial sanction (FS)
- ₹88,13,00,000₹88.13 crore
- Technical sanction (TS)
- ₹51,66,63,279₹51.67 crore
- Tender amount
- ₹49,16,97,029₹49.17 crore
- Current progress
- TS issued once. But TS file is now under scrutiny in PFMS by KIIFB