Pookkottumpadam-Kizhakkethala
Completed100%Physical progress
94%Financial progress
Scheduled start01-10-2020
Scheduled completion17-02-2025
- Contractor
- M/s Malabar Associates
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹43,98,68,946₹43.99 crore
- Amount paid
- ₹41,32,73,494₹41.33 crore
- Paid to contractor
- ₹38,70,06,063₹38.7 crore
- Administrative sanction (AS)
- ₹35,00,00,00,000₹3,500 crore
- Financial sanction (FS)
- ₹1,31,61,52,517₹131.62 crore
- Technical sanction (TS)
- ₹49,96,00,000₹49.96 crore
- Tender amount
- ₹45,78,92,269₹45.79 crore
- Letter of acceptance (LOA)
- ₹45,78,92,269₹45.79 crore
- Current progress
- 8.7 km Work in progress.