Pookottupadam Thampuranttikallu road
Completed100%Physical progress
77%Financial progress
Scheduled start24-09-2020
Scheduled completion26-05-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹44,99,52,930₹45 crore
- Amount paid
- ₹33,74,32,257₹33.74 crore
- Paid to contractor
- ₹31,55,49,557₹31.55 crore
- Administrative sanction (AS)
- ₹35,00,00,00,000₹3,500 crore
- Financial sanction (FS)
- ₹1,15,37,50,000₹115.38 crore
- Technical sanction (TS)
- ₹45,06,14,772₹45.06 crore
- Tender amount
- ₹43,79,68,673₹43.8 crore
- Letter of acceptance (LOA)
- ₹43,79,68,673₹43.8 crore
- Current progress
- under Sub project revision scrutiny in KIIFB. and returned for clarification on 15.07.2021