PWD013-18-05 Chalakudy

Development of Hill Highway SH 59 Improvements from Vellikulangara to Vettilappara bridge in Thrissur district - Contract

Spent on this package so far

₹30.56 crore

₹30,56,38,471

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Flags (1)

Overdue · Vellikulangara- Vettilappara

Scheduled completion was 10-08-2026. That was 53 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Vellikulangara- Vettilappara

In progress
14.9%Physical progress
10.6%Financial progress
Scheduled start11-08-2024
Scheduled completion10-08-2026
Implementing agency (SPV)
KRFB
Contract amount
₹1,08,30,32,392₹108.3 crore
Amount paid
₹11,48,81,745₹11.49 crore
Paid to contractor
₹10,75,79,928₹10.76 crore
Administrative sanction (AS)
₹35,00,00,00,000₹3,500 crore
Financial sanction (FS)
₹1,24,69,19,384₹124.69 crore
Technical sanction (TS)
₹1,07,27,60,000₹107.28 crore
Tender amount
₹1,08,30,32,392₹108.3 crore
Current progress
Placed in TAC on 10.06.2022

Money trail

Estimated amount
₹1,24,69,19,384Estimate of sub-project PWD013-18, shared by 2 contract packages
Expenditure reported · this package
₹30,56,38,471
Expenditure reported · all 2 packages
₹31,02,50,54324.9% of the estimated amount

Details

Project code
PWD013-18-05
Department
Public Works
Constituency
Chalakudy

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Development of Hill Highway SH 59 Improvements from Vellikulangara to Vettilappara bridge in Thrissur district”. The figures below are for that whole project, not this package alone.

Approved
₹1,24,69,19,384₹124.69 crore
Paid so far
₹70,39,52,31656.5% of the amount approved

This package

Work awarded
₹53.79 crorepaid
₹108.3 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.