Peringammala Vithura Road
In progress78%Physical progress
65.2%Financial progress
Scheduled start13-11-2020
Scheduled completion31-08-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹49,64,29,005₹49.64 crore
- Amount paid
- ₹32,35,89,741₹32.36 crore
- Paid to contractor
- ₹30,18,96,803₹30.19 crore
- Administrative sanction (AS)
- ₹35,00,00,00,000₹3,500 crore
- Financial sanction (FS)
- ₹50,80,96,000₹50.81 crore
- Technical sanction (TS)
- ₹47,98,55,000₹47.99 crore
- Tender amount
- ₹49,64,29,005₹49.64 crore
- Current progress
- Work progress 20%., Retaining Wall - 1800/3300 m done Drain - 3000/8500 m casted, 2650/8500 m placed Culvert - 7/18 done, GSB - 2700/9450 m done WMM - 800m done Extension of TOC requested upto 30.11.2022